Larger distributed solar projects wait years for interconnection, Berkeley Lab finds

Larger distributed solar projects wait a median 45 months for permission to operate; residential systems connect in about two months.

•• 1 Min
Larger distributed solar projects wait years for interconnection, Berkeley Lab finds
Larger distributed solar projects wait years for interconnection, Berkeley Lab finds

Larger distributed solar projects now wait a median of 45 months from application to permission to operate (PTO), according to the first national analysis of distribution interconnection timelines and...

Distributed Solar InterconnectionPermission To OperateBerkeley LabInterconnection TimelinesSolar PtoDistribution GridSolar DeploymentInterconnection Costs

Most Popular News

  1. Elgin Commits £400m to 230MW UK Solar-Plus-Storage Portfolio
  2. Optivolt raises $32M to scale intelligent solar module manufacturing
  3. Egypt signs $650 million financing for 1 GW Dandara solar project
  4. Agri-PV apple growing cuts costs by 21.8 percent on Lake Constance
  5. BOS makes up 33% of solar project value, SolarPower Europe finds

Disclaimer


Texts follow.