Larger distributed solar projects wait years for interconnection, Berkeley Lab finds
Larger distributed solar projects wait a median 45 months for permission to operate; residential systems connect in about two months.

Larger distributed solar projects now wait a median of 45 months from application to permission to operate (PTO), according to the first national analysis of distribution interconnection timelines and...