Masdar and Scatec Advance Major Solar Projects in Malaysia and Egypt
Two large-scale solar-plus-storage projects reach key milestones in emerging markets.

Two major solar projects in emerging markets reached critical milestones this week, as Masdar broke ground on a 200-MWac floating photovoltaic plant in Malaysia and Scatec secured financing for the first phase of a 569-MW solar-plus-storage facility in Egypt. Both projects are backed by long-term power purchase agreements and target commercial operation in 2028.
Masdar, together with Citaglobal and TIZA Global, has started construction on the Chereh Dam floating solar plant in Pahang, Malaysia. The project has a capacity of 200 MWac, equivalent to more than 300 MWp, and will span approximately 950 acres. Financing of about MYR 580 million ($143 million) from three international lenders closed on October 27, Masdar announced on October 29. The debt was provided in Malaysian ringgit, though the lenders were not named in the statement.
The project company, Chereh Solar Sdn Bhd, will sell the electricity output to national utility Tenaga Nasional Berhad (TNB) under a 21-year power purchase agreement signed in December 2025. The consortium secured the site through Malaysia's Large Scale Solar (LSS) Cycle 5+ tender, achieving the lowest tariff in the floating solar category. That tender round approved 13 projects totaling 1,975 MWac, including a separate 500-MWac quota for floating solar installations, according to the energy transition ministry PETRA.
The Chereh project represents 40 percent of the 500-MWac floating quota and roughly 10 percent of all capacity approved in the LSS PETRA 5+ round. It is expected to supply electricity equivalent to the consumption of 100,000 homes and create 1,500 jobs during development and construction, Masdar said.
Masdar's First Malaysian Project
Chereh is Masdar's first project in Malaysia and the first under a 10-GW renewable energy roadmap that the Abu Dhabi-based company agreed with the Malaysian Investment Development Authority in 2023. Masdar previously built the 145-MWac (192-MWp) Cirata floating plant in West Java, Indonesia, which opened in November 2023. The company and PLN Nusantara Power have agreed on plans to add up to 500 MW more at Cirata, and Masdar is also studying a floating installation at the Murum reservoir in Sarawak.
"With long-term electricity sales contracted to TNB, the priority now is to deliver the project and bring it into operation," said Mohamad Norza Zakaria, executive chairman and president of Citaglobal and TIZA Global.
The partners have signed a site agreement with Pahang Water & Energy Resources. Masdar expects operations to begin in 2028, and Citaglobal's filing with Bursa Malaysia puts the targeted commercial operation date under the PPA at March 2028.
The project company is held 49 percent by Masdar, 30 percent by Citaglobal Renewable Energy and 21 percent by TIZA Global, according to a Citaglobal filing.
Scatec Closes Financing for Dandara Phase One in Egypt
In Egypt, Scatec has signed $217 million in loans for the first phase of its Dandara solar and battery project and is starting construction, the company said on October 28. This phase combines a 569-MW solar plant with a 100-MWh battery energy storage system. Egypt Aluminium will purchase the output under a 25-year power purchase agreement backed by a sovereign guarantee. Scatec expects the facility to generate approximately 1.4 TWh per year.
The non-recourse debt comes from the European Bank for Reconstruction and Development (EBRD), the African Development Bank and the European Investment Bank. The EBRD, which describes the plant as 500 MW, said on October 29 that its contribution is $63 million. In April, the bank had disclosed a loan of up to $80 million for the project.
The first phase represents an estimated capex of $271 million, of which $217 million, or about 80 percent, is non-recourse debt. National Bank of Egypt will take a 20 percent stake. About 60 percent of the project sits in an Egypt platform that Scatec and the EBRD agreed on October 22, split 60/40 between them. Scatec plans to add equity partners and use equity bridge loans, deferring its own cash until construction ends. The company is also serving as the EPC contractor and O&M provider.
The Dandara project is part of a larger framework. A March 2025 PPA covers a total of 1.1 GW of solar and 200 MWh of storage. The first phase accounts for 569 MW of solar and 100 MWh of storage. Scatec currently holds 56 percent of Dandara, with 36 percent through its EBRD platform and 20 percent directly.
Egypt Aluminium is the country's largest industrial power user and exports about 60 percent of its metal to Europe, Scatec said in 2025. The EBRD also arranged $265 million in October for the 1.2-GW Nefer Minya solar plant.
"Egypt is one of our most important markets, and Dandara reinforces our position as a long-term contributor to the country's energy transition," Scatec CEO Terje Pilskog said.
Commercial operation of the first phase is targeted for the first half of 2028. Scatec expects to begin construction on the second phase in the first half of 2027.
The Dandara first phase represents roughly 18 percent of Egypt's total 3,247 MW of installed solar PV capacity at the end of 2025, based on IRENA data.