BESS contract pitfalls shift risk onto asset owners, experts warn
Techno-legal reviews surge as warranty clauses leave buyers with unprovable claims and hidden liabilities.

Demand is rising for techno-legal reviews of battery energy storage system (BESS) procurement contracts as asset owners discover that warranty clauses are often written in ways that are nearly impossible to enforce. Industry experts warn that standard contract language shifts risk onto buyers and locks them into premature decommissioning timelines.
Volytica Diagnostics, an independent battery diagnostic software provider based in Dresden and founded by Claudius Jehle, has identified six recurring contract patterns that systematically disadvantage asset owners. The company reports that typical BESS procurement contracts run hundreds of pages and span ESG annexes, biocide regulations and noise tables — yet many reviewers miss the problematic clauses buried within.
Warranty clauses that cannot be proven
A core issue centers on end-of-life (EOL) definitions. Many contracts define EOL as the point at which battery State of Health (SoH) falls below 65%, or 20 years after the Commercial Operation Date, whichever comes first. Yet a battery is not dead just because it passes a contractual threshold — electrochemistry sets the real lifespan, and proper maintenance can extend BESS life well past the warranty period.
The problem is that warranty clauses often require conditions that buyers cannot realistically prove. Annual capacity tests determine SoH under perfect, OEM-friendly conditions, but those results do not reflect real-world dispatchable capacity. Factors such as state-of-charge drift and cell imbalance reduce available energy, and a gap of 3% to 6% typically exists between DC racks and the AC grid meter. Warranted capacity and dispatchable capacity are therefore two different figures.
One asset manager at a large European energy supplier told Solar World News: "We have a lot of assets underperforming on capacity and availability. The frustrating part is that the warranty clauses are written so loosely that we can barely act on them. At some point we may have to challenge these contracts outright."
Disputes over ambiguous key performance indicator (KPI) definitions have already cost hundreds of thousands of euros over 10-year project lifespans. Availability is often measured as a binary on/off metric despite the operational nuances of partial availability. Full-cycle-equivalent (FCE) and SoH definitions are frequently left undefined or ambiguous in contracts.
Unrealistic usage profiles and missing baselines
Volytica's analysis shows that usage profiles in BESS contracts are often overengineered and unrealistic. One example profile demands 1.53 FCE per day with 20% idling — a pattern that bears little resemblance to actual market operations. Capacity test protocols are frequently left untouched and written to favor OEMs, while basic battery baseline data is missing from contracts entirely.
The "deploy, deploy, deploy" culture across the renewable energy industry undermines technical diligence, according to the firm. Price erosion across solar, wind and storage components is driving a race to the bottom, and C-suites prioritize deployment volume over thorough contract review. Too many professionals from different backgrounds work on contracts without the specialized knowledge needed to spot technical risks.
Arthur Claire, Secretary General of the Energy Storage Contract Alliance (ESCA), described the industry's structural problem: "Every storage project ends up asking the same questions, and until now the answers were mostly written by the BESS integrators, without many choices for the buyer but to accept them. ESCA exists to give the industry a shared, open baseline, so that a performance guarantee is clearly defined, and key parameters to be monitored during the project lifecycle are written in the procurement contract, and understood by both parties."
A push for open contract baselines
ESCA has developed a model contract backed by 40 GWh of projects that offers an open baseline for performance guarantees. The model contract aims to define key parameters clearly so that both buyers and integrators share a common understanding of what is being guaranteed and how it will be measured.
A BESS is a collection of hundreds of thousands of cells, and warranty clauses function more like insurance policies than technical lifespan guarantees. The real determinant of system longevity is electrochemistry and operational management, not contractual thresholds. Industry professionals advise asset owners to invest in independent techno-legal reviews before signing procurement contracts and to ensure that baseline performance data is captured at the commissioning stage.
For solar industry professionals and investors tracking the storage market, the takeaway is clear: standard BESS contracts contain structural asymmetries that favor integrators. Without independent technical review and clearly defined, provable KPIs, asset owners risk signing agreements that offer warranty protection in name only.